Deliverables: Based on the Scope of Work, the following deliverables and products shall be submitted:
Deliverable 1: Conduct a 3-day training workshop (Workshop 1) on data collection. Two digital copies – in English and in French – of the full workshop curriculum, including questionnaires, manuals, presentations and all other training materials developed for REGIDESO and distributed to the participants.
Deliverable 2: Conduct a 4-day site visit to various power plants across the country to collect data necessary for developing an operational load flow model. Two digital copies – in English and in French – of a brief report on data collected, difficulties encountered in the process and recommendations for mitigating these challenges.
Deliverable 3: Conduct a 5-day training program (Training 1), including all necessary theoretical and practical elements, to prepare REGIDESO to develop and/or improve its national load flow models for the existing network topology. Two digital copies – in English and in French – of the full workshop curriculum, including manuals, presentations and all other training materials developed for REGIDESO and distributed to the participants.
Deliverable 4: Two digital copies – in English and in French – of the Operational Model and Training Report, comprising the developed models critical overview, recommendations for future steps, training overview and conclusions about the overall productiveness of the training.
Deliverable 5: Two draft copies – in English and in French – of the Operational Load Flow Model and Model Creation Report to be submitted to USEA and REGIDESO for their review.
Deliverable 6: Two digital final copies – in English and in French – of the Operational Load Flow Model and Model Creation Report incorporating updates and responses to USEA and REGIDESO’s comments.
Deliverable 7: Conduct a second 5-day training program (Training 2) to further enhance REGIDESO, NELSAP and EAPP planning personnel’s modeling and analytical capacity. Two digital copies – in English and in French – of the full workshop curriculum, including manuals, presentations and all other training materials developed for REGIDESO, NELSAP and EAPP and distributed to the participants.
Deliverable 8: Two digital copies – in English and in French – of the 2nd Training Report on approach, accomplishments and recommendations.
Deliverable 9: Conduct a third 5-day training program (Training 3), including all necessary theoretical and practical elements, to further advance REGIDESO, NELSAP and EAPP’s planning personnel’s capacity. Two digital copies – in English and in French – of the full workshop curriculum, including manuals, presentations and all other training materials developed for REGIDESO, NELSAP and EAPP and distributed to the participants.
Deliverable 10: Two digital copies – in English and in French – of the 3rd Training Report. The Report will include an Executive Summary, findings, recommendations, and annexes.
Deliverable 11: Two draft copies – in English and in French – of the Report on detailed load flow and security (N-1) analyses focusing on impediments to fully evacuating electricity produced by the generating stations associated with the Burundi Power network, undertaken in cooperation with NELSAP, TANESCO, EUCL and EDCL. The Report shall include recommendations for solutions to alleviate network congestion, including remedial dispatch actions, equipment upgrades, and additional transmission investment. A draft copy to be submitted to USEA, NELSAP and REGIDESO for their review.
Deliverable 12: Two digital final copies - in English and in French – of the Report on detailed load flow and security (N-1) analyses incorporating updates and responses to USEA, NELSAP and REGIDESO’s comments.
Reporting
The consultants will report to USEA.
Schedule
The project is expected to begin in June 2019 and take approximately 12 months to complete.
Task(s)
|
Activities
|
Deliverables
|
Target Completion Date
|
1 and 2. Workshop1 & Data Collection Site Visits
|
Conduct 3-day workshop;
4-day Data Collection Site Visits
|
Workshop materials;
Data for load flow model;
Brief data collection report
|
July 31, 2019
|
3. Training 1
|
Conduct 5-day training to prepare REGIDESO to develop and/or improve its national load flow models for the existing network topology
|
Training materials;
Training report
|
August 30, 2019
|
4. Operational Load Flow Model
|
Develop, fine-tune and validate the model
|
Operational Load Flow Model
|
October 31, 2019
|
5. Training 2
|
Conduct 5-day training on advanced contingency analyses, Inertia/Governor load flow calculations, PV, QV analysis and reactive power
|
Training materials;
Training report
|
November 30, 2019
|
6. Training 3
|
Conduct 5-day training on dynamic models’ development and analyses
|
Training materials;
Training report
|
February 28, 2020
|
7. Security Analyses Report
|
Perform load flow and security analyses
|
Report
|
May 29, 2020
|
These target completion dates are provided solely for information purposes and the benefit of bidders. Modification of these assignment dates will not constitute a change in scope.